González-Cruz, M.; Ballesteros-Pérez, P.; Lucko, G.; Zhang, J. (2022). Critical Duration Index: Anticipating Project Delays From Deterministic Schedule Information. Journal of Construction Engineering and Management. 148(11):1-12. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002387
Por favor, use este identificador para citar o enlazar este ítem: http://hdl.handle.net/10251/190356
Título: | Critical Duration Index: Anticipating Project Delays From Deterministic Schedule Information | |
Autor: | Lucko, Gunnar Zhang, Jing-Xiao | |
Entidad UPV: |
|
|
Fecha difusión: |
|
|
Resumen: |
[EN] Classical scheduling techniques are well-known to underestimate the average project duration, yet they remain widely used in practice due to their simplicity. In this paper, the new Critical Duration Index (CDI) is ...[+]
|
|
Palabras clave: |
|
|
Derechos de uso: | Reserva de todos los derechos | |
Fuente: |
|
|
DOI: |
|
|
Editorial: |
|
|
Versión del editor: | https://doi.org/10.1061/(ASCE)CO.1943-7862.0002387 | |
Código del Proyecto: |
...[+] |
|
Agradecimientos: |
This research is supported by the National Social Science Fund projects (No. 20BJY010); National Social Science Fund Post-Financing Projects (No. 19FJYB017); Sichuan-Tibet Railway Major Fundamental Science Problems Special ...[+]
|
|
Tipo: |
|