Non-linear time-cost trade-off models of activity crashing: Application to construction scheduling and project compression with fast-tracking

RiuNet: Repositorio Institucional de la Universidad Politécnica de Valencia

Compartir/Enviar a

Citas

Estadísticas

  • Estadisticas de Uso

Non-linear time-cost trade-off models of activity crashing: Application to construction scheduling and project compression with fast-tracking

Mostrar el registro completo del ítem

Ballesteros-Pérez, P.; Elamrousy, KM.; González-Cruz, M. (2019). Non-linear time-cost trade-off models of activity crashing: Application to construction scheduling and project compression with fast-tracking. Automation in Construction. 97:229-240. https://doi.org/10.1016/j.autcon.2018.11.001

Por favor, use este identificador para citar o enlazar este ítem: http://hdl.handle.net/10251/196277

Ficheros en el ítem

Metadatos del ítem

Título: Non-linear time-cost trade-off models of activity crashing: Application to construction scheduling and project compression with fast-tracking
Autor: Ballesteros-Pérez, Pablo Elamrousy, Kamel Mohammed González-Cruz, María-Carmen
Entidad UPV: Universitat Politècnica de València. Escuela Técnica Superior de Ingenieros Industriales - Escola Tècnica Superior d'Enginyers Industrials
Fecha difusión:
Resumen:
[EN] When shortening a project's duration, activity crashing, fast-tracking and substitution are the three most commonly employed compression techniques. Crashing generally involves allocating extra resources to an activity ...[+]
Palabras clave: Time-cost trade-off , Crashing , Scheduling , Compression , Fast-tracking , Construction
Derechos de uso: Reserva de todos los derechos
Fuente:
Automation in Construction. (issn: 0926-5805 )
DOI: 10.1016/j.autcon.2018.11.001
Editorial:
Elsevier
Versión del editor: https://doi.org/10.1016/j.autcon.2018.11.001
Código del Proyecto:
info:eu-repo/grantAgreement/Chartered Institute of Building//BLJ2016%2FBJL.01//Weather-wise: working with the weather to improve building construction/
info:eu-repo/grantAgreement/UoR//NE%2FR008876%2F1//NERC (Environmental Risks to Infrastructure Innovation Programme)/
Agradecimientos:
This research was supported by the CIOB Bowen Jenkins Legacy Research Fund (reference BLJ2016/BJL.01) and by NERC under the Environmental Risks to Infrastructure Innovation Programme (reference NE/R008876/1) at the University ...[+]