dc.description.abstract | [EN] This research describes the managerial approaches that contractors follow to determine different types of contingencies in construction project management. Two large Spanish general contractors were selected for an in-depth analysis. Interviews and surveys were conducted with six additional companies to explore the external validity of the findings. Managers constrain time and cost buffers through project objectives, applying heuristics to determine inventory buffers. The management of capacity buffers is entrusted to subcontractors. The contractors take advantage of scope and quality buffers to meet project objectives but rarely share these buffers with the owner, unless the owner is an internal client. | es_ES |
dc.language | Inglés | es_ES |
dc.publisher | John Wiley & Sons | es_ES |
dc.relation.ispartof | Project Management Journal | es_ES |
dc.rights | Reserva de todos los derechos | es_ES |
dc.subject | Buffer | es_ES |
dc.subject | Contingency | es_ES |
dc.subject | Risk management | es_ES |
dc.subject | Project | es_ES |
dc.subject | Uncertainty | es_ES |
dc.subject.classification | PROYECTOS DE INGENIERIA | es_ES |
dc.title | Determining Contingencies in the Management of Construction Projects | es_ES |
dc.type | Artículo | es_ES |
dc.identifier.doi | 10.1177/8756972819827389 | es_ES |
dc.rights.accessRights | Abierto | es_ES |
dc.contributor.affiliation | Universitat Politècnica de València. Departamento de Ingeniería de la Construcción y de Proyectos de Ingeniería Civil - Departament d'Enginyeria de la Construcció i de Projectes d'Enginyeria Civil | es_ES |
dc.description.bibliographicCitation | Ortiz-González, JI.; Pellicer, E.; Molenaar, KR. (2019). Determining Contingencies in the Management of Construction Projects. Project Management Journal. 50(2):226-242. https://doi.org/10.1177/8756972819827389 | es_ES |
dc.description.accrualMethod | S | es_ES |
dc.relation.publisherversion | https://doi.org/10.1177/8756972819827389 | es_ES |
dc.description.upvformatpinicio | 226 | es_ES |
dc.description.upvformatpfin | 242 | es_ES |
dc.type.version | info:eu-repo/semantics/publishedVersion | es_ES |
dc.description.volume | 50 | es_ES |
dc.description.issue | 2 | es_ES |
dc.relation.pasarela | S\398430 | es_ES |
dc.description.references | Adafin, J., Wilkinson, S., Rotimi, J. O. B., & Odeyinka, H. (2014). Accuracy in Design Stage Cost Estimating through Risk-contingency Analysis: A Theoretical Exploration. Construction Research Congress 2014. doi:10.1061/9780784413517.151 | es_ES |
dc.description.references | Ballard, G., & Howell, G. (1998). Shielding Production: Essential Step in Production Control. Journal of Construction Engineering and Management, 124(1), 11-17. doi:10.1061/(asce)0733-9364(1998)124:1(11) | es_ES |
dc.description.references | Barraza, G. A. (2011). Probabilistic Estimation and Allocation of Project Time Contingency. Journal of Construction Engineering and Management, 137(4), 259-265. doi:10.1061/(asce)co.1943-7862.0000280 | es_ES |
dc.description.references | Blomquist, T., Hällgren, M., Nilsson, A., & Söderholm, A. (2010). Project-as-Practice: In Search of Project Management Research that Matters. Project Management Journal, 41(1), 5-16. doi:10.1002/pmj.20141 | es_ES |
dc.description.references | Chan, E. H., & Au, M. C. (2009). Factors Influencing Building Contractors’ Pricing for Time-Related Risks in Tenders. Journal of Construction Engineering and Management, 135(3), 135-145. doi:10.1061/(asce)0733-9364(2009)135:3(135) | es_ES |
dc.description.references | De la Cruz, M. P., del Caño, A., & de la Cruz, E. (2006). Downside Risks in Construction Projects Developed by the Civil Service: The Case of Spain. Journal of Construction Engineering and Management, 132(8), 844-852. doi:10.1061/(asce)0733-9364(2006)132:8(844) | es_ES |
dc.description.references | Ford, D. N. (2002). Achieving Multiple Project Objectives through Contingency Management. Journal of Construction Engineering and Management, 128(1), 30-39. doi:10.1061/(asce)0733-9364(2002)128:1(30) | es_ES |
dc.description.references | González, V., Alarcón, L. F., & Molenaar, K. (2009). Multiobjective design of Work-In-Process buffer for scheduling repetitive building projects. Automation in Construction, 18(2), 95-108. doi:10.1016/j.autcon.2008.05.005 | es_ES |
dc.description.references | Guest, G., Bunce, A., & Johnson, L. (2006). How Many Interviews Are Enough? Field Methods, 18(1), 59-82. doi:10.1177/1525822x05279903 | es_ES |
dc.description.references | Günhan, S., & Arditi, D. (2007). Budgeting Owner’s Construction Contingency. Journal of Construction Engineering and Management, 133(7), 492-497. doi:10.1061/(asce)0733-9364(2007)133:7(492) | es_ES |
dc.description.references | Hällgren, M., & Wilson, T. L. (2008). The nature and management of crises in construction projects: Projects-as-practice observations. International Journal of Project Management, 26(8), 830-838. doi:10.1016/j.ijproman.2007.10.005 | es_ES |
dc.description.references | Harbuck R. H. (2004). Competitive bidding for highway construction projects (pp. ES91–ES94). Morgantown, WV: AACE International Transactions. | es_ES |
dc.description.references | HORMAN, M., & KENLEY, R. (1998). Process Dynamics: Identifying a Strategy for the Deployment of Buffers in Building Projects. International Journal of Logistics Research and Applications, 1(3), 221-237. doi:10.1080/13675569808962049 | es_ES |
dc.description.references | Horman, M. J., & Thomas, H. R. (2005). Role of Inventory Buffers in Construction Labor Performance. Journal of Construction Engineering and Management, 131(7), 834-843. doi:10.1061/(asce)0733-9364(2005)131:7(834) | es_ES |
dc.description.references | Howell, G., Laufer, A., & Ballard, G. (1993). Interaction between Subcycles: One Key to Improved Methods. Journal of Construction Engineering and Management, 119(4), 714-728. doi:10.1061/(asce)0733-9364(1993)119:4(714) | es_ES |
dc.description.references | Howell, G., Laufer, A., & Ballard, G. (1993). Uncertainty and project objectives. Project Appraisal, 8(1), 37-43. doi:10.1080/02688867.1993.9726884 | es_ES |
dc.description.references | Idrus, A., Fadhil Nuruddin, M., & Rohman, M. A. (2011). Development of project cost contingency estimation model using risk analysis and fuzzy expert system. Expert Systems with Applications, 38(3), 1501-1508. doi:10.1016/j.eswa.2010.07.061 | es_ES |
dc.description.references | Laryea, S., & Hughes, W. (2011). Risk and Price in the Bidding Process of Contractors. Journal of Construction Engineering and Management, 137(4), 248-258. doi:10.1061/(asce)co.1943-7862.0000293 | es_ES |
dc.description.references | Leach, L. (2003). Schedule and Cost Buffer Sizing: How to Account for the Bias between Project Performance and Your Model. Project Management Journal, 34(2), 34-47. doi:10.1177/875697280303400205 | es_ES |
dc.description.references | Lee, S., Peña-Mora, F., & Park, M. (2006). Reliability and Stability Buffering Approach: Focusing on the Issues of Errors and Changes in Concurrent Design and Construction Projects. Journal of Construction Engineering and Management, 132(5), 452-464. doi:10.1061/(asce)0733-9364(2006)132:5(452) | es_ES |
dc.description.references | Oviedo-Haito, R. J., Jiménez, J., Cardoso, F. F., & Pellicer, E. (2014). Survival Factors for Subcontractors in Economic Downturns. Journal of Construction Engineering and Management, 140(3), 04013056. doi:10.1061/(asce)co.1943-7862.0000811 | es_ES |
dc.description.references | Pellicer, E., Sanz, M. A., Esmaeili, B., & Molenaar, K. R. (2016). Exploration of Team Integration in Spanish Multifamily Residential Building Construction. Journal of Management in Engineering, 32(5), 05016012. doi:10.1061/(asce)me.1943-5479.0000438 | es_ES |
dc.description.references | Pellicer, E., & Victory, R. (2006). IMPLEMENTATION OF PROJECT MANAGEMENT PRINCIPLES IN SPANISH RESIDENTIAL DEVELOPMENTS. International Journal of Strategic Property Management, 10(4), 233-248. doi:10.3846/1648715x.2006.9637555 | es_ES |
dc.description.references | Rooke, J., Seymour, D., & Fellows, R. (2004). Planning for claims: an ethnography of industry culture. Construction Management and Economics, 22(6), 655-662. doi:10.1080/014461904200026324 | es_ES |
dc.description.references | Slauson N. P. (2005). The effectiveness of the construction contract (pp. PM121–PM127). Morgantown, WV: AACE International Transactions. | es_ES |
dc.description.references | Tah, J. H. M., Thorpe, A., & McCaffer, R. (1993). Contractor project risks contingency allocation using linguistic approximation. Computing Systems in Engineering, 4(2-3), 281-293. doi:10.1016/0956-0521(93)90052-x | es_ES |
dc.description.references | Taylor, J. E., Dossick, C. S., & Garvin, M. (2011). Meeting the Burden of Proof with Case-Study Research. Journal of Construction Engineering and Management, 137(4), 303-311. doi:10.1061/(asce)co.1943-7862.0000283 | es_ES |
dc.description.references | Thal, A. E., Cook, J. J., & White, E. D. (2010). Estimation of Cost Contingency for Air Force Construction Projects. Journal of Construction Engineering and Management, 136(11), 1181-1188. doi:10.1061/(asce)co.1943-7862.0000227 | es_ES |
dc.description.references | Thamhain, H. (2013). Managing Risks in Complex Projects. Project Management Journal, 44(2), 20-35. doi:10.1002/pmj.21325 | es_ES |
dc.description.references | Yeo, K. T. (1990). Risks, Classification of Estimates, and Contingency Management. Journal of Management in Engineering, 6(4), 458-470. doi:10.1061/(asce)9742-597x(1990)6:4(458) | es_ES |
dc.subject.ods | 09.- Desarrollar infraestructuras resilientes, promover la industrialización inclusiva y sostenible, y fomentar la innovación | es_ES |