Delay Factors: A Comparative Analysis between Road Infrastructure and Building Projects

RiuNet: Repositorio Institucional de la Universidad Politécnica de Valencia

Compartir/Enviar a

Citas

Estadísticas

  • Estadisticas de Uso

Delay Factors: A Comparative Analysis between Road Infrastructure and Building Projects

Mostrar el registro completo del ítem

Sanchez, O.; Castañeda, K.; Mejía, G.; Pellicer, E. (2020). Delay Factors: A Comparative Analysis between Road Infrastructure and Building Projects. American Society of Civil Engineers. 223-231. https://doi.org/10.1061/9780784482889.024

Por favor, use este identificador para citar o enlazar este ítem: http://hdl.handle.net/10251/168229

Ficheros en el ítem

Metadatos del ítem

Título: Delay Factors: A Comparative Analysis between Road Infrastructure and Building Projects
Autor: Sanchez, Omar Castañeda, Karen Mejía, Guillermo Pellicer, Eugenio
Entidad UPV: Universitat Politècnica de València. Departamento de Ingeniería de la Construcción y de Proyectos de Ingeniería Civil - Departament d'Enginyeria de la Construcció i de Projectes d'Enginyeria Civil
Fecha difusión:
Resumen:
[EN] Delay is one of the most common, complex and risky phenomena that adversely affects performance of construction projects. Several studies have been conducted on delay factors identification, some focused on road ...[+]
Palabras clave: Construction management , Project management , Infrastructure , Project delay , Comparative studies , Infrastructure construction , Contracts and subcontracts , Highways and roads
Derechos de uso: Reserva de todos los derechos
ISBN: 978-0-7844-8288-9
Fuente:
Construction Research Congress 2020: Project Management and Controls, Materials, and Contracts.
DOI: 10.1061/9780784482889.024
Editorial:
American Society of Civil Engineers
Versión del editor: https://doi.org/10.1061/9780784482889.024
Título del congreso: ASCE Construction Research Congress (CRC 2020)
Lugar del congreso: Tempe, Arizona
Fecha congreso: Marzo 08-10,2020
Descripción: This material may be downloaded for personal use only. Any other use requires prior permission of the American Society of Civil Engineers. This material may be found at https://doi.org/10.1061/9780784482889.024
Tipo: Comunicación en congreso Capítulo de libro

References

Abdellatif H. & Alshibani A. (2019). "Major factors causing delay in the delivery of manufacturing and building projects in Saudi Arabia." Buildings 9(4) 93. https://doi.org/10.3390/buildings904009310.3390/buildings9040093

Aibinu A. A. & Odeyinka H. A. (2006). "Construction delays and their causative factors in Nigeria." Journal of Construction Engineering and Management 132

(7) 667-677. https://doi.org/10.1061/(asce)0733-9364(2006)132:7(667)10.1061/(ASCE)0733-9364(2006)132:7(667) [+]
Abdellatif H. & Alshibani A. (2019). "Major factors causing delay in the delivery of manufacturing and building projects in Saudi Arabia." Buildings 9(4) 93. https://doi.org/10.3390/buildings904009310.3390/buildings9040093

Aibinu A. A. & Odeyinka H. A. (2006). "Construction delays and their causative factors in Nigeria." Journal of Construction Engineering and Management 132

(7) 667-677. https://doi.org/10.1061/(asce)0733-9364(2006)132:7(667)10.1061/(ASCE)0733-9364(2006)132:7(667)

Akogbe R. K. T. M. Feng X. & Zhou J. (2013). "Importance and ranking evaluation of delay factors for development construction projects in Benin." KSCE Journal of Civil Engineering 17(6) 1213–1222. https://doi.org/10.1007/s12205-013-0446-210.1007/s12205-013-0446-2

Al-Hazim N. Salem Z. A. & Ahmad H. (2017). "Delay and cost overrun in infrastructure projects in Jordan." In Procedia Engineering(Vol. 182 pp. 18–24). The Author(s). https://doi.org/10.1016/j.proeng.2017.03.10510.1016/j.proeng.2017.03.105

Alaghbari W. Kadir M. R. A. Salim A. & Ernawati. (2007). "The significant factors causing delay of building construction projects in Malaysia." Engineering Construction and Architectural Management 14(2) 192–206. https://doi.org/10.1108/096999807107313010.1108/09699980710731308

Amoatey C. T. Ameyaw Y. A. Adaku E. & Famiyeh S. (2015). "Analysing delay causes and effects in Ghanaian state housing construction projects." International Journal of Managing Projects in Business 8(1) 198–214. https://doi.org/10.1108/IJMPB-04-2014-003510.1108/IJMPB-04-2014-0035

Amoatey C. T. & Okanta A. (2017). "Exploring critical road project delay factors in Ghana." Journal of Facilities Management 15(2) 110–127. Retrieved from https://doi.org/10.1108/JFM-09-2016-003610.1108/JFM-09-2016-0036

Aziz R. F. & Abdel-Hakam A. A. (2016). "Exploring delay causes of road construction projects in Egypt." Alexandria Engineering Journal 55(2) 1515–1539. https://doi.org/10.1016/j.aej.2016.03.00610.1016/j.aej.2016.03.006

Durdyev S. Omarov M. & Ismail S. (2017). "Causes of delay in residential construction projects in Cambodia." Cogent Engineering 4(1) 1–12. https://doi.org/10.1080/23311916.2017.129111710.1080/23311916.2017.1291117

El-Razek M. E. A. Bassioni H. A. & Mobarak A. M. (2008). "Causes of delay in building construction projects in Egypt." Journal of Construction Engineering and Management 134

(11) 831-841. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:11(831)10.1061/(ASCE)0733-9364(2008)134:11(831)

Famiyeh S. Amoatey C. T. & Adaku E. (2017). "Major causes of construction time and cost overruns." Journal of Engineering Design and Technology 15(2) 181–198. https://doi.org/10.1108/JEDT-11-2015-007510.1108/JEDT-11-2015-0075

Kaliba C. Muya M. & Mumba K. (2009). "Cost escalation and schedule delays in road construction projects in Zambia." International Journal of Project Management 27(5) 522–531. https://doi.org/10.1016/j.ijproman.2008.07.00310.1016/j.ijproman.2008.07.003

Kaming P. F. Olomolaiye P. O. Holt G. D. & Harris F. C. (1997). "Factors influencing construction time and cost overruns on high-rise projects in Indonesia." Construction Management and Economics 1(15) 83–94. https://doi.org/10.1080/01446199737313210.1080/014461997373132

Khair K. Mohamed Z. Mohammad R. Farouk H. & Ahmed M. A. (2017). "A management framework to reduce delays in road construction projects in Sudan." Arabian Journal for Science and Engineering. https://doi.org/10.1007/s13369-017-2806-6

Mahamid I. (2017a). "Analysis of schedule deviations in road construction projects and the effects of project physical characteristics." Journal of Financial Management of Property and Construction 22(2) 192–210. https://doi.org/10.1108/jfmpc-07-2016-003110.1108/JFMPC-07-2016-0031

Mahamid I. (2017b). "Schedule delay in Saudi Arabia road construction projects: size estimate determinants and effects." International Journal of Architecture Engineering and Construction 6(3) 51–58. https://doi.org/10.7492/IJAEC.2017.01710.7492/IJAEC.2017.017

Mahamid I. Bruland A. & Dmaidi N. (2012). "Causes of delay in road construction projects." Journal of Management in Engineering 28(3) 300–310. https://doi.org/10.1061/(asce)me.1943-5479.000009610.1061/(ASCE)ME.1943-5479.0000096

. S. K. P. (2013). CAUSES OF DELAY IN INDIAN TRANSPORTATION INFRASTRUCTURE PROJECTS. International Journal of Research in Engineering and Technology, 02(11), 71-80. doi:10.15623/ijret.2013.0211013

Rachid Z. Toufik B. & Mohammed B. (2018). "Causes of schedule delays in construction projects in Algeria." International Journal of Construction Management 3599 1–11. https://doi.org/10.1080/15623599.2018.1435234

Santoso D. & Soeng S. (2016). "Analyzing delays of road construction projects in Cambodia: causes and effects." Journal of Management in Engineering 32(6) 1–11. https://doi.org/10.1061/(ASCE)ME.1943-5479.000046710.1061/(ASCE)ME.1943-5479.0000467

Venkateswaran C. B. & Murugasan R. (2017). "Time delay and cost overrun of road over bridge (ROB) construction projects in India." Journal of Construction in Developing Countries 22(November) 79–96. https://doi.org/10.21315/jcdc2017.22.supp1.510.21315/jcdc2017.22.supp1.5

[-]

recommendations

 