dc.description.abstract | [EN] Classical scheduling techniques are well-known to underestimate the average project duration, yet they remain widely used in practice due to their simplicity. In this paper, the new Critical Duration Index (CDI) is proposed. This index indirectly allows anticipation for the probability of a project ending late, as well as the average project duration extension compared with a deterministic project duration estimate. The accuracy of two simple regression expressions that use the CDI was tested on two representative data sets of 4,100 artificial and 108 empirical (real) projects. Results show that these regression expressions outperformed the only alternative index found in the literature. Besides allowing enhanced forecasting possibilities, calculating the CDI only requires basic scheduling information that is available at the planning stage. It can thus be easily adopted by project managers to improve their project duration estimates over prior deterministic techniques. | es_ES |
dc.description.sponsorship | This research is supported by the National Social Science Fund projects (No. 20BJY010); National Social Science Fund Post-Financing Projects (No. 19FJYB017); Sichuan-Tibet Railway Major Fundamental Science Problems Special Fund (No. 71942006); Qinghai Natural Science Foundation (No. 2020-JY-736); List of Key Science and Technology Projects in China's Transportation Industry in 2018-International Science and Technology Cooperation Project (Nos. 2018-GH-006 and 2019-MS5-100); Emerging Engineering Education Research and Practice Project of Ministry of Education of China (No. E-GKRWJC20202914); Shaanxi Province Higher Education Teaching Reform Project (No. 19BZ016); and Humanities and Social Sciences Research Project of the Ministry of Education (21XJA752003). | es_ES |
dc.language | Inglés | es_ES |
dc.publisher | American Society of Civil Engineers | es_ES |
dc.relation.ispartof | Journal of Construction Engineering and Management | es_ES |
dc.rights | Reserva de todos los derechos | es_ES |
dc.subject | Project | es_ES |
dc.subject | Scheduling | es_ES |
dc.subject | Delays | es_ES |
dc.subject | Forecasting | es_ES |
dc.subject | Regression | es_ES |
dc.subject.classification | PROYECTOS DE INGENIERIA | es_ES |
dc.title | Critical Duration Index: Anticipating Project Delays From Deterministic Schedule Information | es_ES |
dc.type | Artículo | es_ES |
dc.identifier.doi | 10.1061/(ASCE)CO.1943-7862.0002387 | es_ES |
dc.relation.projectID | info:eu-repo/grantAgreement/NSFC//71942006-4/ | es_ES |
dc.relation.projectID | info:eu-repo/grantAgreement/MOST//2018-GH-006/ | es_ES |
dc.relation.projectID | info:eu-repo/grantAgreement/MOST//2019-MS5-100/ | es_ES |
dc.relation.projectID | info:eu-repo/grantAgreement/MOE//E-GKRWJC20202914/ | es_ES |
dc.relation.projectID | info:eu-repo/grantAgreement/MOE//21XJA752003/ | es_ES |
dc.relation.projectID | info:eu-repo/grantAgreement/Education Department of Shaanxi Province//19BZ016/ | es_ES |
dc.relation.projectID | info:eu-repo/grantAgreement/NSSFC//20BJY010/ | es_ES |
dc.relation.projectID | info:eu-repo/grantAgreement/NSSFC//19FJYB017/ | es_ES |
dc.relation.projectID | info:eu-repo/grantAgreement/Natural Science Foundation of Qinghai//2020-JY-736/ | es_ES |
dc.rights.accessRights | Abierto | es_ES |
dc.contributor.affiliation | Universitat Politècnica de València. Escuela Técnica Superior de Ingenieros Industriales - Escola Tècnica Superior d'Enginyers Industrials | es_ES |
dc.description.bibliographicCitation | González-Cruz, M.; Ballesteros-Pérez, P.; Lucko, G.; Zhang, J. (2022). Critical Duration Index: Anticipating Project Delays From Deterministic Schedule Information. Journal of Construction Engineering and Management. 148(11):1-12. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002387 | es_ES |
dc.description.accrualMethod | S | es_ES |
dc.relation.publisherversion | https://doi.org/10.1061/(ASCE)CO.1943-7862.0002387 | es_ES |
dc.description.upvformatpinicio | 1 | es_ES |
dc.description.upvformatpfin | 12 | es_ES |
dc.type.version | info:eu-repo/semantics/publishedVersion | es_ES |
dc.description.volume | 148 | es_ES |
dc.description.issue | 11 | es_ES |
dc.relation.pasarela | S\469710 | es_ES |
dc.contributor.funder | Ministry of Education of China | es_ES |
dc.contributor.funder | National Social Science Fund of China | es_ES |
dc.contributor.funder | Natural Science Foundation of Qinghai | es_ES |
dc.contributor.funder | Education Department of Shaanxi Province | es_ES |
dc.contributor.funder | Ministry of Science and Technology, China | es_ES |
dc.contributor.funder | National Natural Science Foundation of China | es_ES |
dc.subject.ods | 08.- Fomentar el crecimiento económico sostenido, inclusivo y sostenible, el empleo pleno y productivo, y el trabajo decente para todos | es_ES |
dc.subject.ods | 09.- Desarrollar infraestructuras resilientes, promover la industrialización inclusiva y sostenible, y fomentar la innovación | es_ES |