Ballesteros-Pérez, P.; Cerezo-Narváez, A.; Otero-Mateo, M.; Pastor-Fernández, A.; Vanhoucke, M. (2019). Performance comparison of activity sensitivity metrics in schedule risk analysis. Automation in Construction. 106:1-11. https://doi.org/10.1016/j.autcon.2019.102906
Por favor, use este identificador para citar o enlazar este ítem: http://hdl.handle.net/10251/195704
Título: | Performance comparison of activity sensitivity metrics in schedule risk analysis | |
Autor: | Cerezo-Narváez, Alberto Otero-Mateo, Manuel Pastor-Fernández, Andrés Vanhoucke, Mario | |
Entidad UPV: |
|
|
Fecha difusión: |
|
|
Resumen: |
[EN] In Schedule Risk Analysis (SRA), activity sensitivity metrics measure the importance of activities in a project schedule. Highly sensitive activities are those more likely to increase project duration variability ...[+]
|
|
Palabras clave: |
|
|
Derechos de uso: | Reconocimiento - No comercial - Sin obra derivada (by-nc-nd) | |
Fuente: |
|
|
DOI: |
|
|
Editorial: |
|
|
Versión del editor: | https://doi.org/10.1016/j.autcon.2019.102906 | |
Código del Proyecto: |
|
|
Agradecimientos: |
The first author acknowledges the Spanish Ministry of Science, Innovation and Universities for his Ramon y Cajal contract (RYC-2017-22222) co-funded by the European Social Fund. The first four authors also acknowledge the ...[+]
|
|