Climate and construction delays: case study in Chile

RiuNet: Repositorio Institucional de la Universidad Politécnica de Valencia

Compartir/Enviar a

Citas

Estadísticas

  • Estadisticas de Uso

Climate and construction delays: case study in Chile

Mostrar el registro completo del ítem

Ballesteros Pérez, P.; Del Campo-Hitschfeld, ML.; Gonzalez-Naranjo, MA.; González-Cruz, MC. (2015). Climate and construction delays: case study in Chile. Engineering, Construction and Architectural Management. 22(6):596-621. doi:10.1108/ECAM-02-2015-0024

Por favor, use este identificador para citar o enlazar este ítem: http://hdl.handle.net/10251/65272

Ficheros en el ítem

Metadatos del ítem

Título: Climate and construction delays: case study in Chile
Autor: Ballesteros Pérez, Pablo del Campo-Hitschfeld, Maria Luisa Gonzalez-Naranjo, Manuel Alejandro González-Cruz, María Carmen
Entidad UPV: Universitat Politècnica de València. Departamento de Proyectos de Ingeniería - Departament de Projectes d'Enginyeria
Fecha difusión:
Resumen:
Purpose - Construction projects usually suffer delays, and the causes of these delays and its cost overruns have been widely discussed, the weather being one of the most recurrent. The purpose of this paper is to analyze ...[+]
Palabras clave: Planning , Construction management , Productivity rate , Data analysis , Decision support systems , Construction works
Derechos de uso: Reserva de todos los derechos
Fuente:
Engineering, Construction and Architectural Management. (issn: 0969-9988 ) (eissn: 1365-232X )
DOI: 10.1108/ECAM-02-2015-0024
Editorial:
Emerald
Versión del editor: http://dx.doi.org/10.1108/ECAM-02-2015-0024
Tipo: Artículo

References

Ahn, C. R., & Lee, S. (2013). Importance of Operational Efficiency to Achieve Energy Efficiency and Exhaust Emission Reduction of Construction Operations. Journal of Construction Engineering and Management, 139(4), 404-413. doi:10.1061/(asce)co.1943-7862.0000609

Alaghbari, W., Razali A. Kadir, M., Salim, A., & Ernawati. (2007). The significant factors causing delay of building construction projects in Malaysia. Engineering, Construction and Architectural Management, 14(2), 192-206. doi:10.1108/09699980710731308

Apipattanavis, S., Sabol, K., Molenaar, K. R., Rajagopalan, B., Xi, Y., Blackard, B., & Patil, S. (2010). Integrated Framework for Quantifying and Predicting Weather-Related Highway Construction Delays. Journal of Construction Engineering and Management, 136(11), 1160-1168. doi:10.1061/(asce)co.1943-7862.0000199 [+]
Ahn, C. R., & Lee, S. (2013). Importance of Operational Efficiency to Achieve Energy Efficiency and Exhaust Emission Reduction of Construction Operations. Journal of Construction Engineering and Management, 139(4), 404-413. doi:10.1061/(asce)co.1943-7862.0000609

Alaghbari, W., Razali A. Kadir, M., Salim, A., & Ernawati. (2007). The significant factors causing delay of building construction projects in Malaysia. Engineering, Construction and Architectural Management, 14(2), 192-206. doi:10.1108/09699980710731308

Apipattanavis, S., Sabol, K., Molenaar, K. R., Rajagopalan, B., Xi, Y., Blackard, B., & Patil, S. (2010). Integrated Framework for Quantifying and Predicting Weather-Related Highway Construction Delays. Journal of Construction Engineering and Management, 136(11), 1160-1168. doi:10.1061/(asce)co.1943-7862.0000199

Pérez, P. B., González-Cruz, M. C., & Pastor-Ferrando, J. P. (2010). Analysis of construction projects by means of value curves. International Journal of Project Management, 28(7), 719-731. doi:10.1016/j.ijproman.2009.11.003

Block, P. J., Strzepek, K., Rosegrant, M. W., & Diao, X. (2008). Impacts of considering climate variability on investment decisions in Ethiopia. Agricultural Economics, 39(2), 171-181. doi:10.1111/j.1574-0862.2008.00322.x

Bosher, L. (2013). Built-in resilience through disaster risk reduction: operational issues. Building Research & Information, 42(2), 240-254. doi:10.1080/09613218.2014.858203

Migon, P. (2006). Büdel, J. 1982: Climatic geomorphology. Princeton: Princeton University Press. (Translation of Klima-geomorphologie, Berlin-Stuttgart: Gebrüder Borntraeger, 1977.). Progress in Physical Geography: Earth and Environment, 30(1), 99-103. doi:10.1191/0309133306pp473xx

Choi, T. Y., & Hartley, J. L. (1996). An exploration of supplier selection practices across the supply chain. Journal of Operations Management, 14(4), 333-343. doi:10.1016/s0272-6963(96)00091-5

Choo, H. J., Tommelein, I. D., Ballard, G., & Zabelle, T. R. (1999). WorkPlan: Constraint-Based Database for Work Package Scheduling. Journal of Construction Engineering and Management, 125(3), 151-160. doi:10.1061/(asce)0733-9364(1999)125:3(151)

David, M., Adelard, L., Lauret, P., & Garde, F. (2010). A method to generate Typical Meteorological Years from raw hourly climatic databases. Building and Environment, 45(7), 1722-1732. doi:10.1016/j.buildenv.2010.01.025

Dytczak, M., Ginda, G., Szklennik, N., & Wojtkiewicz, T. (2013). Weather Influence-Aware Robust Construction Project Structure. Procedia Engineering, 57, 244-253. doi:10.1016/j.proeng.2013.04.034

Ekström, M., Jones, P. D., Fowler, H. J., Lenderink, G., Buishand, T. A., & Conway, D. (2007). Regional climate model data used within the SWURVE project – 1: projected changes in seasonal patterns and estimation of PET. Hydrology and Earth System Sciences, 11(3), 1069-1083. doi:10.5194/hess-11-1069-2007

El-Rayes, K., & Moselhi, O. (2001). Impact of Rainfall on the Productivity of Highway Construction. Journal of Construction Engineering and Management, 127(2), 125-131. doi:10.1061/(asce)0733-9364(2001)127:2(125)

FANIRAN, O. O., & CABAN, G. (1998). Minimizing waste on construction project sites. Engineering, Construction and Architectural Management, 5(2), 182-188. doi:10.1108/eb021073

Fowler, H. J., & Kilsby, C. G. (2007). Using regional climate model data to simulate historical and future river flows in northwest England. Climatic Change, 80(3-4), 337-367. doi:10.1007/s10584-006-9117-3

González, P. , González, V. , Molenaar, K. and Orozco, F. (2014), “Analysis of causes of delay and time performance in construction projects”,Journal of Construction Engineering and Management, Vol. 140 No. 1, p. 04013027.

Guan, L. (2009). Preparation of future weather data to study the impact of climate change on buildings. Building and Environment, 44(4), 793-800. doi:10.1016/j.buildenv.2008.05.021

Hallegatte, S. (2009). Strategies to adapt to an uncertain climate change. Global Environmental Change, 19(2), 240-247. doi:10.1016/j.gloenvcha.2008.12.003

Hamzah, N., Khoiry, M. A., Arshad, I., Tawil, N. M., & Che Ani, A. I. (2011). Cause of Construction Delay - Theoretical Framework. Procedia Engineering, 20, 490-495. doi:10.1016/j.proeng.2011.11.192

Hans, E. W., Herroelen, W., Leus, R., & Wullink, G. (2007). A hierarchical approach to multi-project planning under uncertainty. Omega, 35(5), 563-577. doi:10.1016/j.omega.2005.10.004

Hinze, J., & Couey, J. (1989). Weather in Construction Contracts. Journal of Construction Engineering and Management, 115(2), 270-283. doi:10.1061/(asce)0733-9364(1989)115:2(270)

Jones, P. G., & Thornton, P. K. (2013). Generating downscaled weather data from a suite of climate models for agricultural modelling applications. Agricultural Systems, 114, 1-5. doi:10.1016/j.agsy.2012.08.002

Jones, R. N. (2001). Natural Hazards, 23(2/3), 197-230. doi:10.1023/a:1011148019213

KUMARASWAMY, M. M. (1997). Conflicts, claims and disputes in construction. Engineering, Construction and Architectural Management, 4(2), 95-111. doi:10.1108/eb021042

Liu, J. , Shahi, A. , Haas, C.T. , Goodrum, P. and Caldas, C.H. (2014), “Validation methodologies and their impact in construction productivity research”,Journal of Construction Engineering and Management, Vol. 140 No. 10, p. 04014046.

Mahamid, I. (2013). Contractors perspective toward factors affecting labor productivity in building construction. Engineering, Construction and Architectural Management, 20(5), 446-460. doi:10.1108/ecam-08-2011-0074

Marzouk, M., & Hamdy, A. (2013). Quantifying weather impact on formwork shuttering and removal operation using system dynamics. KSCE Journal of Civil Engineering, 17(4), 620-626. doi:10.1007/s12205-013-0301-5

Migliaccio, G. C., Guindani, M., D’Incognito, M., & Zhang, L. (2013). Empirical Assessment of Spatial Prediction Methods for Location Cost-Adjustment Factors. Journal of Construction Engineering and Management, 139(7), 858-869. doi:10.1061/(asce)co.1943-7862.0000654

Nguyen, L. D., Kneppers, J., García de Soto, B., & Ibbs, W. (2010). Analysis of Adverse Weather for Excusable Delays. Journal of Construction Engineering and Management, 136(12), 1258-1267. doi:10.1061/(asce)co.1943-7862.0000242

Nik, V. M., Sasic Kalagasidis, A., & Kjellström, E. (2012). Statistical methods for assessing and analysing the building performance in respect to the future climate. Building and Environment, 53, 107-118. doi:10.1016/j.buildenv.2012.01.015

Orangi, A., Palaneeswaran, E., & Wilson, J. (2011). Exploring Delays in Victoria-Based Astralian Pipeline Projects. Procedia Engineering, 14, 874-881. doi:10.1016/j.proeng.2011.07.111

Anuar Othman, A., Victor Torrance, J., & Hamid, M. A. (2006). Factors influencing the construction time of civil engineering projects in Malaysia. Engineering, Construction and Architectural Management, 13(5), 481-501. doi:10.1108/09699980610690756

Pewdum, W., Rujirayanyong, T., & Sooksatra, V. (2009). Forecasting final budget and duration of highway construction projects. Engineering, Construction and Architectural Management, 16(6), 544-557. doi:10.1108/09699980911002566

Port, O. , Schiller, Z. , King, R. , Woodruff, D. , Phillips, S. and Carey, J. (1990), “A smarter way to manufacture”,Business Week, No. 30, pp. 110-115.

Poshdar, M. , González, V.A. , Raftery, G.M. and Orozco, F. (2014), “Characterization of process variability in construction”,Journal of Construction Engineering and Management, Vol. 140 No. 11, p. 05014009.

Regnier, E. (2008). Doing something about the weather. Omega, 36(1), 22-32. doi:10.1016/j.omega.2005.07.011

Rogalska, M. , Czarnigowska, A. , Hejducki, Z. and Nahurny, T.O. (2006), “Methods of estimation of building processes duration including weather risk factors”,Building Review, Vol. 1, pp. 37-42 (in Polish).

Rummukainen, M. (2009). State-of-the-art with regional climate models. Wiley Interdisciplinary Reviews: Climate Change, 1(1), 82-96. doi:10.1002/wcc.8

Shahin, A., AbouRizk, S. M., & Mohamed, Y. (2011). Modeling Weather-Sensitive Construction Activity Using Simulation. Journal of Construction Engineering and Management, 137(3), 238-246. doi:10.1061/(asce)co.1943-7862.0000258

Shahin, A., AbouRizk, S. M., Mohamed, Y., & Fernando, S. (2014). Simulation modeling of weather-sensitive tunnelling construction activities subject to cold weather. Canadian Journal of Civil Engineering, 41(1), 48-55. doi:10.1139/cjce-2013-0087

Sun, M., & Meng, X. (2009). Taxonomy for change causes and effects in construction projects. International Journal of Project Management, 27(6), 560-572. doi:10.1016/j.ijproman.2008.10.005

Thomas, H. R., Riley, D. R., & Sanvido, V. E. (1999). Loss of Labor Productivity due to Delivery Methods and Weather. Journal of Construction Engineering and Management, 125(1), 39-46. doi:10.1061/(asce)0733-9364(1999)125:1(39)

Tommelein, I. D. (1998). Pull-Driven Scheduling for Pipe-Spool Installation: Simulation of Lean Construction Technique. Journal of Construction Engineering and Management, 124(4), 279-288. doi:10.1061/(asce)0733-9364(1998)124:4(279)

Vanhoucke, M. (2011). On the dynamic use of project performance and schedule risk information during projecttracking. Omega, 39(4), 416-426. doi:10.1016/j.omega.2010.09.006

White, P., Golden, J. S., Biligiri, K. P., & Kaloush, K. (2010). Modeling climate change impacts of pavement production and construction. Resources, Conservation and Recycling, 54(11), 776-782. doi:10.1016/j.resconrec.2009.12.007

Yogeswaran, K., Kumaraswamy, M. M., & Miller, D. R. A. (1998). Claims for extensions of time in civil engineering projects. Construction Management and Economics, 16(3), 283-293. doi:10.1080/014461998372312

[-]

recommendations

 

Este ítem aparece en la(s) siguiente(s) colección(ones)

Mostrar el registro completo del ítem