Analysis of the project success factor through time, cost, labour, health, safety, environment and quality aspects at PT XYZ

Mostrar el registro completo del ítem

Komarudin, M.; Nugroho, RE. (2022). Analysis of the project success factor through time, cost, labour, health, safety, environment and quality aspects at PT XYZ. International Journal of Production Management and Engineering. 10(1):33-50. https://doi.org/10.4995/ijpme.2022.16021

Por favor, use este identificador para citar o enlazar este ítem: http://hdl.handle.net/10251/180585

Ficheros en el ítem

Metadatos del ítem

Título: Analysis of the project success factor through time, cost, labour, health, safety, environment and quality aspects at PT XYZ
Autor: Komarudin, Moh Nugroho, Rosalendro Eddy
Fecha difusión:
Resumen:
[EN] This study aims to analyze the failure factors of PT. XYZ in 2018 – 2020 in terms of time, cost, labor, Health, Safety, and Environment (HSE), and quality based on the Success Project Factor (SPF). It includes 183 ...[+]
Palabras clave: Success Project Factor , Schedule Performance , Cost Performance , Safety Performance , Productivity Coefficient , Client Satisfaction
Derechos de uso: Reconocimiento - No comercial - Sin obra derivada (by-nc-nd)
Fuente:
International Journal of Production Management and Engineering. (eissn: 2340-4876 )
DOI: 10.4995/ijpme.2022.16021
Editorial:
Universitat Politècnica de València
Versión del editor: https://doi.org/10.4995/ijpme.2022.16021
Agradecimientos:
Mercubuana University
Tipo: Artículo

References

Arianie, G. P., & Puspitasari, N. B. (2017). Perencanaan Manajemen Proyek Dalam Meningkatkan Efisiensi Dan Efektifitas Sumber Daya Perusahaan (Studi Kasus: Qiscus Pte Ltd). Jurnal Teknik Industri, 12(3), 189-196. https://doi.org/10.14710/jati.12.3.189-196

Ayano, E., & Teshome, W. (2018). Factors Contributing for Delay in Government Construction Projects in Oromia, Ethiopia. The International Journal of Business & Management, 6(1), 131-146.

Dharsika, I. G. E., Budiartha, I. N., & Yansen, I. W. (2017). Analisis Kualitas Manajer Proyek Terhadap Pelaksanaan Proyek Konstruksi (Studi Kasus: Di Denpasar dan Badung). Jurnal Spektran, 5(1). https://doi.org/10.24843/SPEKTRAN.2017.v05.i01.p02 [+]
Arianie, G. P., & Puspitasari, N. B. (2017). Perencanaan Manajemen Proyek Dalam Meningkatkan Efisiensi Dan Efektifitas Sumber Daya Perusahaan (Studi Kasus: Qiscus Pte Ltd). Jurnal Teknik Industri, 12(3), 189-196. https://doi.org/10.14710/jati.12.3.189-196

Ayano, E., & Teshome, W. (2018). Factors Contributing for Delay in Government Construction Projects in Oromia, Ethiopia. The International Journal of Business & Management, 6(1), 131-146.

Dharsika, I. G. E., Budiartha, I. N., & Yansen, I. W. (2017). Analisis Kualitas Manajer Proyek Terhadap Pelaksanaan Proyek Konstruksi (Studi Kasus: Di Denpasar dan Badung). Jurnal Spektran, 5(1). https://doi.org/10.24843/SPEKTRAN.2017.v05.i01.p02

Dharma, A. A. B., Putera, I. G. A. A., & Parami, A. A. D. (2017). Manajemen Risiko Keselamatan Dan Kesehatan Kerja (K3) Pada Proyek Pembangunan Jambuluwuk Hotel & Resort. Jurnal Spektran 5(1), 1-87. https://doi.org/10.24843/SPEKTRAN.2017.v05.i01.p06

Frefer, Mahmoud, Haleema, & Almamlook. (2018). Overview Success Criteria and Critical Success Factors in Project Management. Industrial Engineering & Management, 07(01). https://doi.org/10.4172/2169-0316.1000244

Ismiyati, I., Sanggawuri, R., & Handajani, M. Penerapan Manajemen Resiko pada Pembangunan Proyek Perpanjangan Dermaga log (Studi Kasus: Pelabuhan DalamTanjung Emas Semarang). Media Komunikasi Teknik Sipil, 25(2), 209-220. https://doi.org/10.14710/mkts.v25i2.19467

Kamau, M. E., Jane, G., & John, K. (2018). Influence of Human Related Factors on Success of Construction Projects in Kenya. The International Journal of Business & Management, 6(5), 251-283.

Kathongo, S. M. (2017). Total Quality Management Practices and Performance of Rural Electricity Distribution Projects in Kenya. The International Journal of Business & Management, 5(3), 66-71.

Kerzner, H. (2010). Project Management - Best Practices - Achieving Global Excellenc 2nd ed. New York: John Wiley & Sons, Inc., Hoboken, New Jersey

Lesmana, I. P. D., & Antika, E. (2019). Manajemen Proyek Dengan Scrum. Absolute Media.

Maidamisa, A. A. (2017). Comparative Analysis of Activity Duration in Project Management. The International Journal of Business & Management, 5(12), 158-162.

Meiliawan, F., & Nugroho, R. E. (2020). Peningkatan Kualitas Pelayanan PT XYZ Sebagai Badan Sertifikasi ISO. Warta Pendidikan / e-Journal, 4(5), 4-10

Messah, Y. A., Sina, D. A., & Manubulu, C. C. (2013). Analisa Indeks Biaya Untuk Pekerjaan Beton Bertulang Dengan Menggunakan Metode Sni 7394-2008 Dan Lapangan (Studi Kasus Pada Proyek Pembangunan Asrama STIKES Chmk Tahap III). Jurnal teknik sipil, 2(1), 49-62.

Miano, K. J. (2017). Managing Stakeholders Diversity in Determining Project Success: A Stakeholders Matrix Approach. The International Journal of Business & Management, 5(9), 1-4.

Ogolla, P. J., Mugambi, F., & Obwongi, J. (2019). Influence of Project Organizational Risk Management Policy on Performance of Mom-basa County Government Projects, Kenya. The International Journal of Business & Management, 7(5). https://doi.org/10.24940/theijbm/2019/v7/i5/BM1905-013

Rochman, F., & Wahyuni, H. C. (2018). Analisa Pengaruh Pengen-dalian Kinerja Proyek Terhadap Mutu Proyek Konstruksi Dengan Menggunakan Uji Statistika. Jurnal Teknik Industri, 12(1), 01-06. https://doi.org/10.14710/jati.12.1.01-06

Septiawan, D. B., & Bekti, R. (2016). Analysis of Project Construction Delay Using Fishbone Diagram at PT Rekayasa Industri. Journal of business and management, 5(5), 634-650.

Sutawijaya, A. H., & Nawangsari, L. C. (2018). The Strategic of Implementation Health and Safety to Improved Performance Construction Management System (Case in Arcamanic project, Indonesia). International Journal of Engineering & Technology, 7(2.29), 176-181. https://doi.org/10.14419/ijet.v7i2.29.13312

Sutawidjaya, A.H., Nawangsari, L.C. & Djamil, M. (2019). Operasi Strategi & Proses Manajemen. Jakarta: Mitra Wacana Media

Wang, X., & Nagahira, A. (2017). The Impact of User Innovation on New Product Development Project Success in Japanese Firms, Comparative Study between B2B and B2C Projects. The Interna-tional Journal of Business & Management, 5(7), 287-297.

Wicaksono, I.Y. (2016). Analisis Kinerja Pekerja Pada Keterlambatan Proses Fabrikasi Pengerjaan Proyek Coal Fired Boiler Milik PT Alstom Power Esi Surabaya. S.T. Skripsi. Fakultas Teknologi Kelautan Institut Teknologi Sepuluh Nopember: Sura-baya.

Yanova, N. (2015). Assessment of satisfaction with the quality of education: customer satisfaction index. Procedia-Social and Behavioral Sciences, 182, 566-573. https://doi.org/10.1016/j.sbspro.2015.04.782

[-]

recommendations

 